Enter 16 points: 24VDC.
Response time 1.5ms.
Waterproof type.
4 wire type.
Waterproof connector type.
MITSUBISHI PLC hardware implementation
Hardware implementation is mainly for the control cabinet and other hardware design and field construction.
Design control cabinet and the operating table and other parts of the electrical wiring diagram aand wiring diagram A0J2E-E28AR.
Electrical interconnection diagram of each part of the design system.
According to the construction drawings of the site wiring, and carry out a detailed inspection A0J2E-E28AR.
Because the program design and hardware implementation can be carried out at the same time,
So the design cycle of the MITSUBISHI PLC control system can be greatly reduced.
MITSUBISHI PLC online debugging.
On-line debugging is the process that will through the simulation debugging to further carry on the on-line unification to adjust A0J2E-E28AR.
On-line debugging process should be step by step,
From MITSUBISHI PLC only connected to the input device, and then connect the output device, and then connect to the actual load and so on and so on step by step MITSUBISHI A0J2E-E28AR.
If you do not meet the requirements, the hardware and procedures for adjustment.
Usually only need to modify the part of the program can be. Output points: 32 points.
Voltage: AC100 ~ 240V.
OFF leakage current: 3mA.
Output type: bidirectional controlled silicon MITSUBISHI A0J2E-E28AR.
Response time: 0.5Hz+1ms.
8 points / a common end.
38 point terminal station.
With short circuit protection.
With the surge absorber.
Each scanning process. Focus on the input signal sampling. Focus on the output signal to refresh.
Input refresh process MITSUBISHI A0J2E-E28AR. When the input port is closed,
Program in the implementation phase, the input end of a new state, the new state can not be read.
Only when the program is scanned, the new state is read.
A scan cycle is divided into the input sample, the program execution, the output refresh.
The contents of the component image register are changed with the change of the execution of the program.
The length of the scan cycle is determined by the three.
CPU the speed of executing instructions.
Time of instruction.
Instruction count.
Due to the adoption of centralized sampling.
Centralized output mode.
There exist input / output hysteresis phenomena, i.e., the input / output response delay.
PLC selection with the development of PLC technology, more and more types of PLC products,
Function is becoming more and more perfect, and its application is more and more extensive.
Different series of different models of PLC has different performance, applicable occasions also have different emphasis,
Price also has a greater difference. Therefore PLC selection,
Under the premise of meeting the control requirements,
Should consider the best performance to price ratio, a reasonable choice of PLC.
System program memory for storing system program,,
Including management procedures, monitoring procedures, as well as the user program to do the compiler to compile the process of interpretation A0J2E-E28AR.
Read only memory. Manufacturers use, content can not be changed, power does not disappear.
 